The Flow Control (A) opens the valve to supply water to the pipe when demand arises. The Damping Chamber (B) adapts the water flow to the correct capacity in the pipe (normally approx. 1 l/m/s). The Check Valve (C) prevents backflow so that the line maintains the correct capacity when needed.
A tap on the line is opened, changing the pressure across the Check Valve (C), and a signal is sent to the 3E Flow Control (A), which opens the valve to supply water to this pipe.
The pipe fills under the building's normal water pressure (normally 10 m/s) and is cushioned by the 3E Damping Chamber (B) before the water reaches the tap.
The tap is closed, sending a signal to a pump that empties the pipe back into any remaining shortened recirculation loop (3E typically eliminates 90% of all hot water recirculation), leaving an empty pipe.
A flow-through expansion vessel is installed in the property's plant room. This vessel is needed if no one else in the building is using water when a pipe empties, creating a temporary increase in water volume. If water is being used in the building, the vessel remains empty. A vessel with an available volume of 20 litres is normally sufficient for 100 apartments.